Browsing Tag

treehouse construction

The Building Process

Quick Construction Update!

December 10, 2019

So, a quick update…

Getting the steel fabricated and installed has been a challenge.

The structural engineer that did the drawings did a half-ass job and he didn’t include critical measurements on the spacing of the footers, so the contractor had to do them. That took a lot more time and effort than was necessary to get the caissons laid out and set. While it wasn’t perfect, it was close enough to work. Great job Cary from Backcountry Builders!

Then we had an issue with the crane company. The crane broke down and delayed the start. With the delay, the welders that were going to fabricate the steel on site decided the winter weather was going to be too much, so they passed on the job.

Then Cary had to find a new crane and someone who would fabricate the supports offsite and transport them to the job site…which he did! We’re in the process of sorting out how to get nearly 40′ big pre-fabricated support beams (see image above) up road with several switchbacks. Who ever said this was going to be easy!

More updates as soon as we get the steel figured out. Once the steel is up, it should be relatively easy going then – just like building a regular house. Except this one is 40′ in the air!

Happy Holidays everyone and thanks for subscribing to the blog. If you like it. please share with your friends and family. Thank you!

The Building Process

Zen Treehouse Foundation

October 18, 2019
Treehouse foundation for one beam
Caisson – one of 25 – prior to concrete pour

The 25 caissons are finally drilled, set with rebar and ready for concrete (coming tomorrow- more pics after they pour). This is what it takes to hold a 2 bedroom, 2 bath, 1600 square foot luxury treehouse 40 feet in the air.

The picture below shows how the contractors had to dig down to bedrock, drill into the rock (you can see the rock dust around the rebar), and set the rebar into the rock for this engineered foundation. VERY complicated.

The surveyors had to come out once to mark the foundation, again after the tubes were set to confirm the foundations, and then will come back one more time after the concrete is poured to determine the exact height of each of the steel beams that will hold up the treehouse. One reason why this is a very expensive way to build a tree house!

More updates next week on the concrete pour. The steel should be going up by early November, so we’ll see some real progress then. Exciting times!

If you like the blog and project, please share with your friends. Would love to get the word out more about this amazing build in the beautiful Rocky Mountains of Colorado.
Cheers friends!

Note the white rock dust from the contractor drilling into the bedrock to place the rebar. The Zen Treehouse isn’t going anywhere! #qualityconstruction
The Building Process

Treehouse Construction Finally Begins!

October 8, 2019

See the little tubes at the lower left of the picture above? Those are the where they will be putting the rebar and concrete that be the foundational support for the metal beams that will hold up the house.

The biggest effort with this was the surveying – to make sure all these were put in EXACTLY the right location so the support beams are in the right location to support the structure properly.

Here’s a few more pics of the work they’ve done and a little accident with the excavator. It’s a very steep site, so it rolled over. Thankfully, no one was hurt!

The foundation should be ready for the steel in the next week or so. I’m not sure that will be so interesting, so won’t be doing another blog post until the steel starts going up in the next few weeks. Stay tuned!

The Building Process Uncategorized

Utilities for a Luxury Treehouse

December 27, 2018

All luxury treehouses need utilities. Water, electric, sewer and gas….and eventually high-speed internet. This post is about some great progress that happened today on the first three items in the foregoing list.

Treehouse construction; building a treehouse'
Treehouse Utility Installation

In the last post, I mentioned that the well finally hit water at 1,406 feet. Just to put that into perspective, that’s nearly as high as the Empire State Building that is 1,454 feet from its base to the tip of the tower on top. Needless to say, that is a VERY deep water well. But, since we are near the top of a mountain, it’s not that unexpected. We are very high in elevation (about 8,300 feet above sea level) and hundreds of feet above the floor of the valley we overlook. Also, the static level of the water in the well shaft is 700 feet. This means that even though we hit the aquifer at 1,406 feet, the water in the shaft leveled out at 700 feet. This means we have to put our pump at 700 feet instead of 1,406 feet and that we have 8 gallons of water flowing per minute – a VERY good rate of flow. So, other than the fact the well probably cost (I haven’t received the bill yet) about $30,000, we do have a well that seems to have plenty of water and more than we need for our project!

Treehouse Well
The well for the Zen Treehouse is almost as deep as the Empire State Building is tall

In addition to the water well, we are installing electric (currently on the grid, but planning on adding solar), and completing the tie-in to the septic system. The leach field has already been installed and we need to complete the system with the septic tank, which will be placed at the end of the driveway. The gas company, at a later date, will install their gas line and meter – this is something the gas utility only does themselves. But, we will have natural gas instead of propane, which is wonderful!

They expect to finish work on the utilities and backfilling the driveway by January 1st, so I’ll have a new post up just after then.

Happy New Year everyone and here’s to a great 2019. We look forward to opening the Zen Treehouse for reservations during the summer of 2019 for bookings starting in the fall.

The Building Process Uncategorized

Water….Drilling the Well

December 23, 2018
The search for water begins…high atop the mountain

So, we knew when we bought the land that we would have to drill a well. We also knew that drilling a well was not something that was 100% guaranteed to be successful. When we talked to the drilling company, they talked about “witching” a well and that it was the best way to find the best spot to drill. We did have a limited area that the drilling rig could access, so we had them “witch” around the areas that the rig could access and they picked the spot.

Then the day came to drill this past week. They started on a Tuesday. Two days in, I get an email from my contractor. “They are about 1,100 feet down (after telling us that they thought for sure they would hit water around 850 feet) and they have maybe 1/2 gallon an hour (FYI…that’s not enough). Maybe we’ll go to 1,300 and hope for the best.” OMG I thought. We may not have water!

The next day, I worried…most of the day…and I didn’t tell Delinda. I didn’t want her to worry and I was hopeful I could share good news when it happened. Thankfully, that news came. At 1,406 feet (basically 1/4 of a mile down), they hit water and it was flowing at 8 gallons/minute. Better yet, the static level (where the water settled in the bore hole) was 700 feet. That meant that we didn’t need a huge pump to get the water up from 1,4000 feet. So, good news all around!

My daughter Ashley was coming into town for Christmas, so we drove up on Friday afternoon from the airport to check on the progress. By the time we started up the switchbacks, we passed the drilling contractor’s trucks coming down. So, we didn’t get to talk to them. But we did the the finished capped well. We also saw that the IREA (Intermountain Rural Electric Association) had been out to set two electrical poles and lines to our property. So, we now have water and electric! And we have natural gas that we will tap into, which is great so we don’t have to use propane.

So, a big week of progress on the utilities this week. Not super exciting, but necessary! Hope for some more progress in the next few weeks as they set the septic tank and backfill the driveway. Then, the big wait until April until the main treehouse construction starts.

Merry Christmas, Happy Holidays, and Happy New Year to you all! ZEN TREEHOUSE will be open for reservations in fall of 2019!

Peter and Delinda

Treehouse, Colorado Treehouse
The well and the power pole…exciting!
Most of the time we drive up to the property, we see deer…this time was no exception.
The Building Process

Footers and Framing for the Retaining Wall for the Driveway Installed

October 25, 2018

treehouse, treehouse construction, bailey Colorado, Colorado

Driveway Retaining Wall Progress

Great progress on a big part of the project – a massive concrete retaining wall that will hold back the driveway so that it is wide enough for what we need in terms of parking and the crane that will arrive in the spring to begin moving the structural steel. You can see how the mountain drops off. Imagine the walkway from the drive to the main cabin being level with the drive and extending about 15′ out to the front door of the main treehouse cabin. Yes, that makes the entry door VERY high off the ground and up in the trees. Now, imagine walking through the cabin to the back deck the cantilevers off the back of the house and how high in the sky and trees that will be. It will be something to behold! We can’t wait to show you the progress as we build this amazing bit of an architectural gem in the beautiful mountains of Colorado. PS – did you notice the views??

More updates coming soon! The retaining wall should be poured and the septic tank should both be in soon.

Thanks for reading our blog and be sure to share with your friends!