Foundation Progress!

Finally we have some vertical construction progress to report! Approximately 50% of the posts and beams for the project have been installed. The posts are 6 x 6 HSS (hollow structural sections) tubing and are welded to base plates, which in turn are bolted to the caissons. There are a total of 25 posts that…

Zen Treehouse Foundation

The 25 caissons are finally drilled, set with rebar and ready for concrete (coming tomorrow- more pics after they pour). This is what it takes to hold a 2 bedroom, 2 bath, 1600 square foot luxury treehouse 40 feet in the air. The picture below shows how the contractors had to dig down to bedrock,…