The Building Process The Design Process

Amazing Progress! Construction Update with Video – Feb 4 2021

February 4, 2021

We have made really great progress since the last blog, as you’ll be able to see in the video. All the floor decking is in and there is great progress on getting the decks completed. We have to finish putting the deck joists in before we can start putting up walls. The guys had to use the crane with a bucket to lay down the floor joists, which would have been very difficult to do with the walls up. Take a look at the time lapse below to see the day they were working on the floor joists of the main deck.

Since the last video, we also had a long meeting with our interior designers, Eric Mandil from Mandil, Inc. I included a small clip of our conversation with Eric and Sean from Mandil about the finishes selections – from bath and kitchen tile and countertops to the wood flooring and ceiling beams and everything in-between – including the furniture.

The good news is that, with the exception of a couple of pieces of furniture, everything is selected and will be on order soon. They did a great job with the finishes and furnitures selections and think you and our future guests will love how it all works so well together and is comfortable and cozy. We’re excited for the day, about 5 months from now, when we shoot a video and write a blog about the day the furniture and accessories are installed!

If you liked this blog and our Youtube channel, please subscribe and share with your friends and family that might be interested in construction, design, treehouses, mountain homes, luxury properties or unique homes. We’d sure appreciate it!

The Building Process The Design Process

Thanksgiving Construction Update 11/26/2020

November 26, 2020
Treehouse foundation work
Getting closer to completing the steel work. This is a pic of Josh from Native Welding working on the steel for the guest suite.

The steelwork is coming along right on schedule. Josh and his crew from Native Fabrication are doing an amazing job having cleaned up all the unfinished work from our last welding subcontractor and getting the rest of the steel in place in record time.

We met at the site with our General Contractor, Cary Dunn, and our Interior Designers, Eric and Sean from Mandil, Inc. My wife Delinda and I have worked with Eric Mandil for more than a dozen years now. He’s led the design work for all of our restaurant projects. You can see a few pictures of his work at our first Indulge Bistro & Wine Bar location here. Since then, he’s been instrumental in our expansion and vision to build Indulge as a restaurant company focused on the female demographic, with interiors that make women feel comfortable and special.

The design palate for the treehouse
The design palate – floors, cabinets, countertops, backsplash, paint, wallpaper and ceilings.

They put together an amazing palate of materials for the treehouse. The above image shows all the different materials that we will be using. You can see the hardwood floor selection, which will be everywhere except for the bathrooms and kitchen and will be heated using radiant floor heat. The kitchen cabinets, backsplash and countertop samples are sitting at the top on the hardwood floor sample. The bathroom cabinets, countertop and shower tile samples are just below that. The rectangular wood sample is what will cover the exposed beams in the ceiling. The little squares to the right are what will go on the shower floors and a larger 18 x 36 tile of the same style will be the kitchen and bathroom floors. The large tile to the right of the hardwood floor sample is what will be on the fireplace in the living room and the other smaller tile sample will be on the fireplace in the master (but much larger tile size). The wallpaper will be in the bathrooms and you can see the two paint samples on top of the wall paper.

Treehouse construction planning meeting
Treehouse construction planning meeting to make sure everyone is on the same page with materials selections prior to framing getting started.
Café appliances
We chose Café appliances for the treehouse kitchen – they are gorgeous!

Because of all the supply chain disruptions caused by COVID-19, we had to order our appliances now – even though we are 6-7 months from completion – to be sure we have them in time. Three of the six appliances we ordered are on backorder with no firm date for delivery. Ugh. Fingers crossed that they get here by June!

We picked the new line of Café appliances. They have a matte white finish (no fingerprints!) with brushed bronze hardware. It’s a really stunning look that we love. What do you think? If you haven’t heard of this brand before, here’s a blog that goes in depth about them and how much they love these appliances – both how they look and how they function.

I’ll leave you with a short video clip of the steel construction work. They will wrap this up in the next week and then framing will begin by mid-December!

Happy Thanksgiving everyone!

Peter and Delinda

Putting the final pieces in place on the guest cabin foundation.
The Building Process

More Construction Updates

October 5, 2020
Thefirst Youtube ZenTreehouse Channel Video – We will get better!

We posted our first video update on our Youtube Channel that will document the Zen Treehouse construction over the next six months or so. Please subscribe and share with your friends. We want to let the world know about this amazing property that we won’t be keeping for ourselves, but want to share with everyone.

We will be on VRBO and Airbnb, hosting stays for 3 night minimums for as little as $499/night! Wait until you see the amenities that we are including for this rate. Fully stocked wine coolers, fully stocked bars, a luxury relaxation area including a barrel sauna, a hot tub under a pergola, and a fire pit area with Adirondack chairs. What a great place to relax, enjoy a sunset and a glass of wine while you’re relaxing with friends in the hot tub under the stars.

We hope you enjoy the construction update pictures! More to come soon…

Treehouse Construction
It takes two cranes to build a treehouse foundation!
The Building Process Uncategorized

ZenTreehouse is Live Streaming Construction, Sunrises and Sunsets

September 13, 2020

Check our our new NestCam livestream to catch the progress each day and check out the scenery, sunrises and sunsets. The construction at this point is of the steel foundation. It’s a bit of a slow go at this point, but will be accelerating starting in October 2020!

I was up at the building site today and had the Neteo high speed internet installed today so I could install my Outdoor Nest Cam. Since construction (the out of the ground stuff) is starting soon, I thought it would be great to see what’s going on live, make some cool time lapse videos of the progress, check the weather, and see the sunrises and sunsets.

We have electrical at the site, so they were able to install the receiver (like a mini satellite dish) and the router. While the Neteo installer was doing his work, I installed the Nest Cam on a tree to give the best view possible off the building site and the view. Of course, until the steel starts going up, you won’t see much – but when it does, you’ll see the unique foundation we have with 6×6 American made steel beams and large 12″ I-beams. Should be interesting!

I added a pic of where we will be putting the outdoor relaxation area with hot tub, barrel sauna, and fire pit conversation area. Awesome view of Deer Creek Valley!

Let me know what you think once you check out the live stream. Enjoy!

Hot tub barrel sauna fire pit location
This is where the hot tub, barrel sauna and fire pit will go
The Building Process

The Crane Has Arrived!

September 7, 2020
Treehouse construction crane with view
The arrival and set up of the crane to set the steel beams – check out the view!

We finally got our crane onsite today! This means we will now see, over the next five weeks, the house come out of the ground. The crew anticipates they will start on Thursday Sept 10th. I was told that initially it will be slow going, getting everything right with the base plates and initial beams.

They are going to install an extruded steel floor about 10′ under the treehouse structure itself. This is to make maintenance and access underneath to vents, pipes, etc. easier. Once they get this floor installed, they said the rest will be a piece of cake.

So, five weeks puts us into mid-October before they can start framing. The other thing that’s going to happen in October is the installation of the natural gas line. Yes, you read that right – we have natural gas (no propane!) for the treehouse! We will use this gas for the boiler for the radiant heated floors (also serves as our hot water heater for sinks and showers), the two fireplaces inside the house, and a new outdoor relaxation area we are adding somewhere up the hill from the house. This area will feature a barrel sauna, a covered hot tub, and a fire pit with Adirondack chairs for watching sunsets and relaxing after a nice soak or steam. I’ll cover more about what this area will look like in a future post.

I’m excited to get this blog moving – finally – with some frequent updates. Let me know what you think in the comments and please share!

Treehouse construction crane
Testing to be sure they positioned the crane to get the steel to each of the 25 caissons.
The Building Process The Design Process

Video Walkthrough – WOW

July 17, 2020

This is what we are building – a luxury treehouse in the Rocky Mountains of Colorado – only 1 hour drive from Denver. Enjoy a video walkthrough of the property – 100% architecturally correct and to scale. The outside environment and the furnishings are a good representation, but not exact. We have made our furniture and finishes selections, but these can (and most likely will) change by the time we get to furnishing the house in the spring.

We think this video walkthrough is the best way for you to get a feel for how special the Zen Treehouse will be! It really does feel like you’re walking through the finished product. We love how this video turned out!

You’ll be able to stay in this beautiful, unique, and very Zen property starting Spring 2021. The construction is active and at the time of this writing (September 2020), the posts and beams that hold the house up are being installed.

This home is one of six furnished rental properties that we own and operate. We began our furnished rental portfolio nearly ten years ago. We also own four restaurants in town (www.indulgewinebar.com) and have been in the hospitality business for twelve years. We know you’ll love your stay at any one of our properties, but especially at this one! Waiting list will open early 2021. Subscribe to our blog to get notified when we will begin taking reservations!

The Building Process

Quick Construction Update!

December 10, 2019

So, a quick update…

Getting the steel fabricated and installed has been a challenge.

The structural engineer that did the drawings did a half-ass job and he didn’t include critical measurements on the spacing of the footers, so the contractor had to do them. That took a lot more time and effort than was necessary to get the caissons laid out and set. While it wasn’t perfect, it was close enough to work. Great job Cary from Backcountry Builders!

Then we had an issue with the crane company. The crane broke down and delayed the start. With the delay, the welders that were going to fabricate the steel on site decided the winter weather was going to be too much, so they passed on the job.

Then Cary had to find a new crane and someone who would fabricate the supports offsite and transport them to the job site…which he did! We’re in the process of sorting out how to get nearly 40′ big pre-fabricated support beams (see image above) up road with several switchbacks. Who ever said this was going to be easy!

More updates as soon as we get the steel figured out. Once the steel is up, it should be relatively easy going then – just like building a regular house. Except this one is 40′ in the air!

Happy Holidays everyone and thanks for subscribing to the blog. If you like it. please share with your friends and family. Thank you!

The Building Process

Zen Treehouse Foundation

October 18, 2019
Treehouse foundation for one beam
Caisson – one of 25 – prior to concrete pour

The 25 caissons are finally drilled, set with rebar and ready for concrete (coming tomorrow- more pics after they pour). This is what it takes to hold a 2 bedroom, 2 bath, 1600 square foot luxury treehouse 40 feet in the air.

The picture below shows how the contractors had to dig down to bedrock, drill into the rock (you can see the rock dust around the rebar), and set the rebar into the rock for this engineered foundation. VERY complicated.

The surveyors had to come out once to mark the foundation, again after the tubes were set to confirm the foundations, and then will come back one more time after the concrete is poured to determine the exact height of each of the steel beams that will hold up the treehouse. One reason why this is a very expensive way to build a tree house!

More updates next week on the concrete pour. The steel should be going up by early November, so we’ll see some real progress then. Exciting times!

If you like the blog and project, please share with your friends. Would love to get the word out more about this amazing build in the beautiful Rocky Mountains of Colorado.
Cheers friends!

Note the white rock dust from the contractor drilling into the bedrock to place the rebar. The Zen Treehouse isn’t going anywhere! #qualityconstruction
The Building Process Uncategorized

Utilities for a Luxury Treehouse

December 27, 2018

All luxury treehouses need utilities. Water, electric, sewer and gas….and eventually high-speed internet. This post is about some great progress that happened today on the first three items in the foregoing list.

Treehouse construction; building a treehouse'
Treehouse Utility Installation

In the last post, I mentioned that the well finally hit water at 1,406 feet. Just to put that into perspective, that’s nearly as high as the Empire State Building that is 1,454 feet from its base to the tip of the tower on top. Needless to say, that is a VERY deep water well. But, since we are near the top of a mountain, it’s not that unexpected. We are very high in elevation (about 8,300 feet above sea level) and hundreds of feet above the floor of the valley we overlook. Also, the static level of the water in the well shaft is 700 feet. This means that even though we hit the aquifer at 1,406 feet, the water in the shaft leveled out at 700 feet. This means we have to put our pump at 700 feet instead of 1,406 feet and that we have 8 gallons of water flowing per minute – a VERY good rate of flow. So, other than the fact the well probably cost (I haven’t received the bill yet) about $30,000, we do have a well that seems to have plenty of water and more than we need for our project!

Treehouse Well
The well for the Zen Treehouse is almost as deep as the Empire State Building is tall

In addition to the water well, we are installing electric (currently on the grid, but planning on adding solar), and completing the tie-in to the septic system. The leach field has already been installed and we need to complete the system with the septic tank, which will be placed at the end of the driveway. The gas company, at a later date, will install their gas line and meter – this is something the gas utility only does themselves. But, we will have natural gas instead of propane, which is wonderful!

They expect to finish work on the utilities and backfilling the driveway by January 1st, so I’ll have a new post up just after then.

Happy New Year everyone and here’s to a great 2019. We look forward to opening the Zen Treehouse for reservations during the summer of 2019 for bookings starting in the fall.

The Building Process Uncategorized

Water….Drilling the Well

December 23, 2018
The search for water begins…high atop the mountain

So, we knew when we bought the land that we would have to drill a well. We also knew that drilling a well was not something that was 100% guaranteed to be successful. When we talked to the drilling company, they talked about “witching” a well and that it was the best way to find the best spot to drill. We did have a limited area that the drilling rig could access, so we had them “witch” around the areas that the rig could access and they picked the spot.

Then the day came to drill this past week. They started on a Tuesday. Two days in, I get an email from my contractor. “They are about 1,100 feet down (after telling us that they thought for sure they would hit water around 850 feet) and they have maybe 1/2 gallon an hour (FYI…that’s not enough). Maybe we’ll go to 1,300 and hope for the best.” OMG I thought. We may not have water!

The next day, I worried…most of the day…and I didn’t tell Delinda. I didn’t want her to worry and I was hopeful I could share good news when it happened. Thankfully, that news came. At 1,406 feet (basically 1/4 of a mile down), they hit water and it was flowing at 8 gallons/minute. Better yet, the static level (where the water settled in the bore hole) was 700 feet. That meant that we didn’t need a huge pump to get the water up from 1,4000 feet. So, good news all around!

My daughter Ashley was coming into town for Christmas, so we drove up on Friday afternoon from the airport to check on the progress. By the time we started up the switchbacks, we passed the drilling contractor’s trucks coming down. So, we didn’t get to talk to them. But we did the the finished capped well. We also saw that the IREA (Intermountain Rural Electric Association) had been out to set two electrical poles and lines to our property. So, we now have water and electric! And we have natural gas that we will tap into, which is great so we don’t have to use propane.

So, a big week of progress on the utilities this week. Not super exciting, but necessary! Hope for some more progress in the next few weeks as they set the septic tank and backfill the driveway. Then, the big wait until April until the main treehouse construction starts.

Merry Christmas, Happy Holidays, and Happy New Year to you all! ZEN TREEHOUSE will be open for reservations in fall of 2019!

Peter and Delinda

Treehouse, Colorado Treehouse
The well and the power pole…exciting!
Most of the time we drive up to the property, we see deer…this time was no exception.